Last week’s update ended with LSSTCam’s refrigeration system in a pressure-hold test and cooldown possibly starting over the weekend. This week the team on Cerro Pachón worked through the final checks on the camera’s refrigeration circuits. Meanwhile another round of winter weather closed the summit road for two days. We are still off sky. Here is where things stand as of October 23.
Camera
The four refurbished cryo circuits passed pressure hold tests late last week. Compressor spin tests were cleared, and the camera team completed tests of the readout electronics’ bulk power supply and of the chiller flow rate. Evacuation of the refrigerant lines began on October 17 and will continue until the refrigerant charge and cooldown steps are ready to commence.
Telescope and optics
The telescope mount will stay at horizon until the camera is cold. Until then the daily routine continued. The mount’s oil supply system ran for up to 5.5 hours a day, the secondary mirror’s hexapod was warmed up, and the primary/tertiary mirror support actuators were bump-tested. A few actuators have been flagged for inspection once the telescope can point to zenith. The filter exchange that began last Friday will get another dedicated session in the coming days.
Power and cooling
Repairs to the summit’s main generator continued, and on October 19 the electrical team ran load tests on the backup generator. Facilities staff stepped the main glycol chiller system down to its winter setpoint and returned it to automatic tracking of ambient temperature. They also swapped a filter in the low-temperature glycol loop, and software tests ran on the PCS chiller.
Dome
On October 15 the dome passed its first full handover checkout since the storm, rotating and opening its louvers and shutter without problems. Work continued on the drive of one dome Light/Wind screen panel.
Auxiliary Telescope
After daytime checks on October 15, AuxTel was declared fully operational and ready to go back on sky. It has stayed under its weather protection since then because of the forecast rain and snow.
Weather and access
Fog and low cloud, winds up to 27 m/s and humidity at 99–100% closed general access to the observatory on October 20 and 21. Simonyi was monitored remotely from La Serena, where the team kept up the daily calibration-system checkouts, hexapod warm-ups and oil-system runs. The camera and electrical teams made short visits to the building on both days. The road reopened on October 22. CFOps continues to be on top of every situational change in the weather to keep everyone safe on the road. And congratulations to the summit and La Serena teams for keeping things moving through another stop-start week.
What’s next
The priorities for the coming days are the camera’s refrigerant charge and cooldown, the first move of the mount to zenith with servicing of the flagged actuators, and completing the filter exchange. Once the camera is cold, calibration and checkout work will follow, if not able to go on sky due to weather. Still more rain is forecasted for the week of October 26, and because of this, we don’t have a return-to-sky date to announce yet. Stay tuned for updates here.