Last week’s update left the camera pumping down and the telescope’s subsystems starting to come back up. This week the team on Cerro Pachón finished the last big preparatory steps before the camera cooldown, despite two more spells of snow. We are still off sky. Here is where things stand as of October 16.
Camera
LSSTCam came through a series of checkouts. On October 8 the camera’s internal filter-changing hardware passed a full mechanical checkout, and the vacuum turbo pumps were spun up and found to work normally. The camera has been pumping since then. On October 9 the shutter was tested and the team took a few test exposures. In parallel, coolant flow was restored to the camera’s supporting systems. The drying of the refrigerant lines, which runs in long sessions under constant watch, finished on October 11. The camera team and the summit refrigeration technicians stayed on the mountain through the holiday weekend to see it through. With new filter-dryers installed, a 26-hour pressure-hold test of the refrigeration system started Thursday. The compressor spin tests, evacuation and refrigerant charge come next, and the cooldown itself could begin as early as this weekend.
Telescope and optics
On October 8 the mechanical team completed the replacement of a strut on the secondary mirror’s hexapod. The next day the hexapod was warmed up, driven through long-range moves and cleared for normal use. On October 9 the team also tested the primary/tertiary mirror’s support actuators and hardpoints with the telescope at horizon, started coolant flow to the mirror cell, and began powering up the telescope mount’s oil supply system. Bump tests of the mirror supports followed on October 11. Preparations are under way for the first filter exchange since the storm, now planned for Friday.
Auxiliary Telescope
After cleaning work on its cryogenic cooler, AuxTel’s instrument, LATISS, reached operating temperature on October 9. That evening the first AuxTel image since the storm arrived on RubinTV. The team is now removing AuxTel’s weather protection and pointing it to zenith to start its own recovery tests.
Power and site systems
On October 12 the summit’s backup generators had preventive maintenance, and the site ran on a rental generator during the work. Afterwards power was switched back to the 750 kVA unit. All parts for the repair of the main generator are now on hand. Two of the building’s air handling units are running again, and a modified filter is keeping the glycol cooling loop running smoothly.
Dome and mechanical work
Motor tests continued on the light-and-wind screen. With the weather clearing, rotation, shutter and louver tests have resumed, and the dome shutters were opened for the first time in several months on Oct 15.
Weather
Snow closed the road again on October 12–14, and the summit was monitored remotely from the Pachón hotel and La Serena. Access reopened to 4x4 vehicles today. Our thanks again to CFOps for keeping the roads cleared and safe.
What’s next
The priorities for the coming days are the camera’s refrigerant charge and cooldown, the filter swap, and continue dome tests. Once the camera is cold, calibration and checkout work will follow. More precipitation is forecast for the week of October 19, and we don’t have a return-to-sky date to announce yet. We’ll keep posting updates here.