Last week’s update described the observatory’s systems coming back to life. This week the team on Cerro Pachón started preparing the systems to go back on sky, while a run of winter weather slowed things down. We are still off sky. Here is where things stand as of October 9.
Camera
LSSTCam reached an important milestone. The camera was connected to its Dynalene coolant supply and powered on all utilities on October 5, followed by the startup of the cryostat pump-down which will continue into next week. Work on the refrigeration system continued in parallel: the final refrigeration circuit passed its pressure-decay test, final cleaning, and the sequence of drying of all the refrigerant lines is set to start this weekend. This drying runs about 12 hours per session and needs constant monitoring, and it is a key step before the camera can be charged with refrigerant and cooled down.
Telescope and optics
The first in-situ wash of the primary mirror was completed on October 3. The replacement of a strut on the secondary mirror’s hexapod was completed on Oct 8. The team also began a full recirculation test of the telescope mount’s oil supply system this week. Start-up tests of the primary/tertiary mirror support and thermal systems was also completed this week, late on Friday.
Power and site systems
Scheduled maintenance on the summit’s 750 kVA generator went ahead on October 1 and repair work on the primary generator unit is next.
Dome and mechanical work
Following last week’s first manual slide-out of a light-and-wind screen panel, motor tests on the screen began this week prior to their installation on the dome.
Weather
The weather set much of this week’s pace: rain and sleet on October 4, gusts of up to 26 m/s on October 5, and snow that closed the road on October 7. Access to the mountain has been limited to 4x4 vehicles most of the week, and the buses were granted access on Friday, although more precipitation is forecasted for the coming days. Our thanks to CFOps for keeping the road and the people on it safe.
What’s next
Next week’s priorities are to try to complete the camera cooldown, the checkout tests of the telescope, dome, and mirror support systems. Due to the variable and unpredictable weather, we don’t have an exact return-to-sky date to announce yet, and will be slowed to some extent by the weather, but we hope it to be in a matter of days rather than weeks for the system to be ready to resume night operations, and we’ll keep posting updates here.
Thanks to the summit staff and teams across camera, optics, mechanical, electrical, electronics, software, facilities, IT, DM and night operations for keeping the work moving through a difficult week.