Summit technical progress (week ending 2026-10-09)

Last week’s update described the observatory’s systems coming back to life. This week the team on Cerro Pachón started preparing the systems to go back on sky, while a run of winter weather slowed things down. We are still off sky. Here is where things stand as of October 9.

Camera
LSSTCam reached an important milestone. The camera was connected to its Dynalene coolant supply and powered on all utilities on October 5, followed by the startup of the cryostat pump-down which will continue into next week. Work on the refrigeration system continued in parallel: the final refrigeration circuit passed its pressure-decay test, final cleaning, and the sequence of drying of all the refrigerant lines is set to start this weekend. This drying runs about 12 hours per session and needs constant monitoring, and it is a key step before the camera can be charged with refrigerant and cooled down.

Telescope and optics
The first in-situ wash of the primary mirror was completed on October 3. The replacement of a strut on the secondary mirror’s hexapod was completed on Oct 8. The team also began a full recirculation test of the telescope mount’s oil supply system this week. Start-up tests of the primary/tertiary mirror support and thermal systems was also completed this week, late on Friday.

Power and site systems
Scheduled maintenance on the summit’s 750 kVA generator went ahead on October 1 and repair work on the primary generator unit is next.

Dome and mechanical work
Following last week’s first manual slide-out of a light-and-wind screen panel, motor tests on the screen began this week prior to their installation on the dome.

Weather
The weather set much of this week’s pace: rain and sleet on October 4, gusts of up to 26 m/s on October 5, and snow that closed the road on October 7. Access to the mountain has been limited to 4x4 vehicles most of the week, and the buses were granted access on Friday, although more precipitation is forecasted for the coming days. Our thanks to CFOps for keeping the road and the people on it safe.

What’s next
Next week’s priorities are to try to complete the camera cooldown, the checkout tests of the telescope, dome, and mirror support systems. Due to the variable and unpredictable weather, we don’t have an exact return-to-sky date to announce yet, and will be slowed to some extent by the weather, but we hope it to be in a matter of days rather than weeks for the system to be ready to resume night operations, and we’ll keep posting updates here.

Thanks to the summit staff and teams across camera, optics, mechanical, electrical, electronics, software, facilities, IT, DM and night operations for keeping the work moving through a difficult week.

6 Likes

Wonderful news! I really hope the alerts will indeed resume within the next week or two. Am I right in understanding that, from the software side, nothing is expected to change? In other words, will the alert structure remain the same, and will everything continue to work the same way on the broker side as well? I’m asking because I developed my pipeline in the spring, and after such a long interruption I’m wondering whether I might suddenly need to modify it because something has changed in the broker interface or in the Rubin alert data format during the downtime.

1 Like

Thank you for these interesting and informative updates,

Regards,
Hal Heaton

1 Like

We’ve been very busy improving the Alert Production pipelines while we have been off sky, but the structure of the alerts has not changed. The change most likely to be relevant for your pipeline is that the alert cutouts will now include the mask plane as a MASKPLANE extension for each of the science, template, and difference cutouts.

2 Likes

@bstalder @isullivan @mschwamb @fed

Summit technical progress (week ending 2026-10-16) ??:thinking:

When will it start again ?

The season to observe the NES and generate templates for the first sectors (RA 0h-2h) is getting short…

Should the SCOC think about taking special measures to be in time with the templates, like take an image every 6 nights, during 1 month to already have at least 2 filters (r and i) - as we need 3 images at least by filter - to be able to do tracking the first year for large distant slow-motion TNOs and not lose one year, as the season is between August and December ? Then for the next sectors beyond RA 2h it shouldn’t be an issue anymore…

Any clarification please ?

1 Like

Thank you for the reminder. Will post it in a few minutes!

We are working on building templates from the images we collected between the early January cutoff of DP2 up until the summit weather shutdown in July, and we will make an announcement when those are ready and deployed. We are simultaneously working on building templates from DECam survey images (such as DELVE), and those should become available incrementally over the coming months. Using templates from a different instrument is new scope and brings new challenges that we need to solve before we can deploy them in production for generating alerts, but we are working hard to build up as much template coverage as quickly as we can.

2 Likes